President Don Jeanes
Guest Contributor
September 2, 2005
This letter was originally e-mailed to the
Milligan campus this summer after preconstruction work for the new convocation
center began. It was submitted to The Stampede in response to the above printed
editorial.
Dear campus:
I realize that there are many mixed feelings over the site preparation work and
clearing of trees for the Convocation Center and Theatre project. That is
certainly understandable. We all value and appreciate the natural beauty of our
campus and work to enhance that as much as possible.
Clarinda and I personally have taken a special interest in improving the
landscaping and aesthetics of campus. In fact we have planted approximately 75
trees since 1997 and we remain committed to that effort. Earlier this week we
welcomed twenty-one friends and alumni to campus as part of the Restoration Crew
that helps us make improvements to our buildings and grounds. In a few weeks we
will be joining together as a campus to devote a work day to these same efforts
as we prepare for our students to return. These work groups are all focused on
improving our appearance. I appreciate everyone's commitment to and interest in
the college's initiatives. This means that we are all passionate about the
mission and life of this institution, and that is encouraging.
As much as anyone, I had hoped we could save the large oak tree next to the
tennis courts. But the ultimate conclusion reached recently by the architects,
builder, and our planning committee, including Dick Major, was that it was not
possible to do so due to the sewer, electrical, and water lines running all
around and under the tree. We were informed that the construction work itself
would seriously damage the tree and its root system and the backfill from
extending the commons would result in several feet of additional soil being
placed around the base of the tree. It also became evident that all the other
trees in the construction area needed to come down, as well, due to site
preparation work (they will be grading and filling in the slope from the Commons
area down towards the road). We are also doing site work for phase two; I don't
know when it will be built but doing the infrastructure now will be less
expensive and less disruptive now than in years to come. We were disheartened by
this conclusion but realize that it is in the best interest of the college.
It is certainly a stark view right now but I ask you to be patient with the
process and patient with us as we work through this process. The end result will
be a beautiful and long-awaited facility to serve our theatre program and entire
campus community. In addition to the facility, the new landscaping, new trees,
and entire commons area will further enhance our campus' natural beauty in some
new and exciting ways as that center area of campus becomes more alive and
inviting than ever before.
We will be working to further explain the construction process to you along the
way in each stage. We are sorry that the tree cutting caught everyone by
surprise; the contractor for taking down the trees had to leave for a 4-6 week
job in middle Tennessee. Our goal will be to provide as much information in
advance as possible about the process. I hope that all can be supportive of the
project; it certainly advances the college and is a fulfillment of our
commitment when we took the theatre out of Derthick. Admittedly, the process
will at times be painful, but the end result will be something with which I
think we will all be proud and pleased.
Thank you,
Don